§ 18C-44. Underground storage tank system installation, repair, modification, or closure plan check permit required.
Latest version.
An underground storage tank system and its ancillary components subject to H&SC Chapter
6.7 and CCR Title 23 shall not be installed, repaired, modified, or closed unless an installation, repair,
modification, or closure plan review permit is issued to the owner or operator of
the underground storage tank, or their authorized designee. A plan review permit application
shall be submitted to the CUPA, on forms furnished by the CUPA, and the applicable
fee as set forth in Santa Barbara County Code chapter 15, or its successor chapter, paid to the CUPA prior to the issuance of a plan review
permit.
(Ord. No. 5072, 2-5-2019)